Krampitz large tank / storage tank cluster
Krampitz large tank – storage tank cluster for mining, industry, diesel power plants…
The Krampitz large tank farm. Ideal for mining, industry and power plants. Effective fuel supply. Even for the really big ones.
Transporting and setting up the large tank is extremely easy thanks to the containerized design and standardized equipment.
Construction of Krampitz large tank farm
First step: set strip foundations. Once the foundations have hardened, the tank containers can be erected. A crane and two fitters are required to assemble the containers. First the administrator. The heart of the facility. Receiving and dispensing unit for fuel. The central control for the entire cluster is also here. From here, the fill levels of each individual container are managed and the entire safety sensor system is monitored. Is it standing? Administrator container, like any other container, it is anchored at all corners with retaining bolts.
Now: Attach pipe fittings. The next container is mounted on this. This container and all others that will be set up now are the workers. The fuel is stored here. 60.000 liters per container. The Filling and emptying the worker containers runs via the collecting lines. The inflow and outflow is controlled via motorized ball valves, switched by the control module in the Worker. This control module is the Central control in the administrator subordinate.
Set up a large tank
Setting up the workers is always the same: place pipe fittings, align containers, screw in retaining bolts. Same thing to the right of the administrator container. A total of 10 worker containers with a total capacity of 600.000 liters will be assembled here. You can also enlarge the system and add additional containers. Even in retrospect. Dismantling and assembling at another location is just as easy. All you have to do here is set the appropriate strip foundations.
The containers are there, now it follows Assembly of external tank equipment on the administrator, air filter for ventilation and ventilation, electronic content display for each tank chamber, a motorized ball valve in the suction pipe of the container.
Also: lightning protection, lamps for external lighting and a circumferential safety railing on the tank roof. The same elements are also mounted on all worker containers.
At the end they will Control modules of the worker containers are electrically connected to the central control in the administrator container. In addition, the piping systems are tested for leaks.
Made. The large tank system is ready for operation after approx. 7 days. The system is filled via the administrator container. More than 15 tanker trucks can be unloaded professionally. Then the tank farm is full. Fuel is dispensed for mobile and stationary consumers on the other side of the administrator container.
We keep things moving. Storage tank cluster from Krampitz. Cubic good.